RENEWABLES - BOMEN SOLAR FARM
Our first investment is now operational ā with construction completed under budget. Despite COVID-19 affecting commissioning, hold
point testing has been completed and the farm has been operational and able to export 100% of generation since mid-June 2020
Project Snapshot
Capacity
Total cost at completion
~120.5 MW DC (~100 MW AC)
-$180m(1) (~$8m under budget)
SKI Acquires
Bomen Solar Farm
April 2019
Expected Revenue (P50)
Gearing
O&M and Asset Management
Key Success Factors
~$13.5m p.a. for first 5 years(2)
~70%
Beon Energy Solutions (Beon) and RES
Strong partnerships with Beon (EPC and O&M), TransGrid (Connection), Westpac (PPA 1)
and Flow Power (PPA 2)
Optimised design to add an additional 0.5MWDC
ā Construction delivered under budget by Beon and TransGrid
Strong grid location with robust MLF and no system strength issues identified
Provided around 200 jobs during construction with a focus on local jobs and supporting
local businesses
Community focus - in partnership with Westpac, established a fund to invest $1 million
over ten years in community initiatives
New
South
Wales
(1) Includes purchase of land, construction costs, construction of dedicated transmission line and capitalised interest during construction
(2) Average annual revenue considering PPA agreements, loss factors and plant output on P50 forecast
Spark Infrastructure I Investor Presentation | August 2020
&
Construction
Complete
June 2019
Construction
Commences
Wagga
North
substation
Jan 2020
&
Byrnes Road
March 2020
AEMO
Registration
Operational
June 2020
Northern
Development
Area
Southern
Development
Area
Trahairs Road
PPAs
-95%
contracted for the
first five years
-82%
contracted for the
first 10 years
Transmission line
corridor
East Bomen Road
10km to Wagga Wagga
PPA Counterparties
10 YEARS
Westpac
5,7, & 10 YEARS
Flow Power