2021 Investor Presentation

Meridian's NZ transmission costs $M Meridian actual 116 Meridian actual 120 100 82 80 60 40 20 0 FY20 actual FY21 actual New Zealand policy and regulation Transmission Pricing Methodology (TPM) EA published final TPM guidelines in June 2020 Replaces current HVDC and RCPD charges with benefit-based and residual charges Transpower released its proposed new TPM in August 2021 EA currently consulting on the full proposed TPM With the aim for a new TPM to take effect for prices from 1 April 2023 Trustpower's judicial review was heard in the High Court in October 2021, decision has been reserved 140 Meridian. Transpower estimate assuming 1 April 2023 implementation 67 new TPM (FY24) Source: Meridian, Transpower NOVEMBER 2021 2021 INVESTOR PRESENTATION 6