SEMPRA 5-Year Capital Plan
Port Arthur LNG Phase 1
A world-class energy infrastructure project with top-tier partners + customers
TARGET OWNERSHIP 1
•
SEMPRA™
INFRASTRUCTURE
25%
KKR Denali + Other
45%
ConocoPhillips
30%
•
•
HIGHLIGHTS
Strategic partners ConocoPhillips + KKR
✓ 100% of current contractable capacity
secured with long-duration contracts and
high-quality counterparties
Closed $6.8B project-level, non-recourse debt
financing
Target COD Train 1 2027, Train 2 2028
Commenced civil construction program with
150+ pieces of equipment on site led by Bechtel
LNG trains + storage tank areas almost cleared;
soil stabilization has started
Placed major long-lead time orders with APCI
and Baker Hughes
1.
Demonstrative only and actual ownership may vary. Represents SI Partners' targeted project-level ownership of 25%. Sempra owns 70% of SI Partners, which will result in
Sempra's net ownership of 17.5% (25% x 70%).
SEMPRA 10View entire presentation