Investor Presentaiton
On Going Programme
PTC India
•
•
•
•
Increase Discom participation and Discom Integration at all stages not only net-metering:
SRISTI ("Sustainable Rooftop Implementation for Solar Transfiguration in India")
On Going Programme on Rooftop Solar (RTS) Implementation:
Central Financial Assistance (CFA) of 5,000 Cr. for Grid Connected Rooftop up to FY 2019-20
4,200MW Implementation (out of a total target of 10,000MW) was planned through CFA by the year FY 2019-20
Implemented by State Nodal Agencies (SNA's), Solar Energy Corporation of India (SECI), Public Sector Undertakings
(PSUs) and other Government Agencies (GAs).
The total installed capacity of grid-connected rooftop solar panels in India is 2.3 gigawatts (GW),
well short of the 2022 target of 40GW.
There is a gap in RTS implementation.
Issues in Implementation of the scheme :
Multiple tenders by different agencies and subsequently considerable delay in tendering.
•
Involvement of multiple stakeholder viz. SNAs, DisComs, PSUs, Developers etc.
•
Reluctance of DisComs due to revenue loss; availability of net meter; CEIG inspection etc.View entire presentation