Minas-Rio Impairment Considerations and Project Delivery
CONTINUING PROGRESS DURING THE PAST 12 MONTHS
At end of 2012
At end 2011
Beneficiation plant
Earthworks nearing completion
Concrete poured
•
Release of caves for construction
Tailings dam land access
92%
79,000 m³
4 of 4 (September 2012)
21 of 21 secured
79%
29,000 m³
2 of 4
8 of 21 secured
•
3 legal injunctions cleared
Transmissions line
•
Installation licence
×
December 2012
* outstanding
•
Towers available / in construction
43
0
Pipeline
•
Track released for construction
Landowners released
Filtration plant and Port
•
Overall completion of filtration plant
Mechanical erection at port
Transmission line towers installed for port
Licences and Permits
Pending licences and permits
402 km; 247 km installed
95%
219 km; 201 installed
88%
77%
65%
85%
45%
11%
41%
17 (to be issued up to FOOS)
78