Minas-Rio Impairment Considerations and Project Delivery slide image

Minas-Rio Impairment Considerations and Project Delivery

CONTINUING PROGRESS DURING THE PAST 12 MONTHS At end of 2012 At end 2011 Beneficiation plant Earthworks nearing completion Concrete poured • Release of caves for construction Tailings dam land access 92% 79,000 m³ 4 of 4 (September 2012) 21 of 21 secured 79% 29,000 m³ 2 of 4 8 of 21 secured • 3 legal injunctions cleared Transmissions line • Installation licence × December 2012 * outstanding • Towers available / in construction 43 0 Pipeline • Track released for construction Landowners released Filtration plant and Port • Overall completion of filtration plant Mechanical erection at port Transmission line towers installed for port Licences and Permits Pending licences and permits 402 km; 247 km installed 95% 219 km; 201 installed 88% 77% 65% 85% 45% 11% 41% 17 (to be issued up to FOOS) 78 8