REGULATORY CHANGE (2/3)
Contract Reference Factor (FRC)*
COES published the technical procedure PR-25, which reduces only the SoP of Transportation from
100% to a fraction of it called FRC
FRC
June 1, 2021 - April 30, 2025
Will be determined as the quotient
between the volume of gas
required according to the projected
I dispatch of the COES and the
I volume required at effective
power of the unit. (COES maintains
that it should be one for rainy season
\ and another for low water levels)
Technology
FRC
Plant
M m3/day
Open Cycle
Combined Cycle
11.44%
Chilca Dos
332.54
65.74%
Chilca Uno
2,259.14
*Resolution of the board of directors, Supervisory Agency for Investment in Energy and Mining OSINERGMIN N° 096-2021-OS/CD
ENGIE Energía Perú