29 ASSET OPTIMISATION CONSORT OPERATIONS - LOM OF 6 YEARS • Extraction of Prince Consort ('PC') Shaft pillar • . · PC Shaft pillar - Mineral Resource of 48,820t @ 25.54g/t for 40Koz Development to PC Shaft pillar completed in May 2020 - first target block with proved Mineral Reserve of 5,000 tons at av. grade of 25g/t Forecast production of ~3,900oz to 7,800oz per annum from PC shaft pillar at steady-state • Life of project forecasted at 3 years Targeting all-in sustaining cost of -USD1,200/oz Maximise Consort plant capacity PAN AFRICAN RESOURCES • . Process additional surface source material at Consort plant to maximise plant capacity Exploration • 36 exploration targets have been identified at New Consort and will be explored during the 3 years of PC Shaft pillar mining Initial sampling revealed grades in excess of 300g/t, containing large amounts of visible gold