Access Bridge www.cgxenergy.com cgx energy inc Contract Summary Component Name: Construction of Access Bridge Progress: 100% Completed Timeline: 6th April 2021 to 23rd December 2021 Contractor: Home Designs Engineering Associates (Berbice) Particulars: Connects Corentyne highway to access road - Specifications - 40 tons per axle capacity 8m x 15m prestressed concrete - 1m dedicated pedestrian walkway 28