(4) The assistance required for completing Polavaram Project
Phase - I
Phase - II
Fund required for completion of Polavaram Irrigation Project
Head Works from +41.15 Mts to +45.72 Mts
Polavaram National Project - Irrigation Component
Funds needed from Govt. of India for
completion of Phase-I - EL +41.15m
Sl.No.
Rs. in Crore
1
YEAR
2019-20
Land Acquisition
WORKS
and R&R
Miscellaneous
Rs. in Crore
TOTAL
Apr-19
200
2,000
40
2,240
May-19
225
3,000
80
3,305
*Amount required for main works (As on 9 April 2018)
2,874.68
Jun-19
225
4,500
80
4,805
Jul-19
150
5,000
75
5,225
*Amount required for land acquisition and R & R
2,494.11
Aug-19
125
4,500
60
4,685
(as on 21st October 2018)
Sep-19
150
3,000
55
3,205
Amount already utilized, and reimbursement
3342.40
Oct-19
350
1,500
60
1,910
from Government of India due (as on 17th December 2018)
Nov-19
300
800
55
1,155
TOTAL
8,711.19
Dec-19
375
525
64
964
GRAND TOTAL
2,100
24,825
569
27,494
*These estimates are based on information available so far, and are subject to
correction as the project work progresses.
These are rough estimates as on 9th April 2018. Figures are subject to revision