Investor Presentaiton slide image

Investor Presentaiton

Expansion -Project Status Expansion Additional Capacity Status Update Greenfield Expansion at Panna (IU) with Hamirpur(GU) Grey cement plant of 4 MnTPA & WHR power generation of 22 MW Work is in progress as per schedule - Panna Around 50% civil construction has been done with significant progress in critical structures Pre-Heater & Silos. More than 70% fabrication work is also done. Equipment deliveries and erection has also started at site. Hamirpur -Civil activity of foundations and silo construction is progressing. Financial Closure of Consortium Project Loan for Rs 1680 crores from Banks has been done at Interest Rate of 7.20% p.a. Also availed disbursement of Rs 208 crores. JKcement CAPEX till YTD Dec'21 Expected Date of Completion Rs.961 crores March'23 13
View entire presentation