Investor Presentaiton
Expansion -Project Status
Expansion
Additional
Capacity
Status Update
Greenfield
Expansion at
Panna (IU) with
Hamirpur(GU)
Grey cement
plant of 4 MnTPA
& WHR power
generation of 22
MW
Work is in progress as per schedule -
Panna Around 50% civil construction
has been done with significant progress in
critical structures Pre-Heater & Silos.
More than 70% fabrication work is also
done. Equipment deliveries and erection
has also started at site.
Hamirpur -Civil activity of foundations
and silo construction is progressing.
Financial Closure of Consortium Project Loan
for Rs 1680 crores from Banks has been done
at Interest Rate of 7.20% p.a. Also availed
disbursement of Rs 208 crores.
JKcement
CAPEX
till YTD
Dec'21
Expected
Date of
Completion
Rs.961
crores
March'23
13View entire presentation