AEL: Summary on Operational and Financial Updates - Q1 FY23
•
Operations
Q1 FY23
Adani New Industries Supply Chain
Ecosystem volume stood at
264 MW
Handled 16.6 Mn Pax movements at
seven operational Airports
123 Lane KMs of Roads constructed
•
Mining Services
o Suliyari mining services made
operational and started production
o Mining Services production volume
up by 71%
IRM volume up by 52%
•
·
Finance
Q1 FY23
Total Income up by 223% to Rs.
41,066 Cr
EBIDTA up by 107% to Rs. 1,965 Cr
Attributable Profit up 73% to Rs.
469 Cr
Others
Q1 FY23
Green H2 Ecosystem
[Consolidated]
Partnership with TotalEnergies
forged to create largest green H2
ecosystem with 25% stake in Adani
New Industries Limited (ANIL)
Roads
Provisional COD received for Bilaspur
HAM Road project
Concession Agreement signed for
Kagal-Satara BOT project of 65 kms
Capital Management
Completed Rs.7,700 Cr primary
equity transaction with IHC
Achieved financial closure for Rs.
6,071 Cr in primary industry vertical
for copper project with consortium
of banks led by SBI
Incubating new wave of infrastructure assets like new energy industries, airports and data centers
adani
Commercial Operation Date
COD
IHC International Holding Company, Abu Dhabi
IRM Integrated Resources Management HAM - Hybrid Annuity Model
BOT Build-Operate-Transfer
13View entire presentation