Key Highlights - Q2FY23
GAR
Crete Airport (Greece)
•
•
Project is fully funded mainly through State Grant which is already received and Airport Modernisation &
Development Tax. It is a debt free Project
~93% of Earth Works completed on Airport side. Works progressing in multiple fronts of Runway, Taxiway,
Apron, Parking area, Fire station and other buildings
•
Terminal Building concreting works are in progress for base slab, foundation and columns
Flood protection works are in progress in both Airport and Access roads
• 15.9% of physical progress achieved as of September 30, 2022
Medan Airport (Indonesia)
•
•
Traffic recovery driven by steady growth in both domestic and international traffic. Domestic traffic recovered
to 81% of 2019 level and international traffic recovered to 75% of 2019 level in October 2022. Overall, total
traffic has recovered 79%
Ministry of Transport, Indonesia has approved increase in Passenger Service charges (PSC). Domestic PSC
has been increased by 27% and International PSC has been increased by 16% w.e.f August 1, 2022
Currently, connected with 18 domestic destinations and 6 international destinations