Gas Supply Security and Business Achievements
Gas Sources
The phase-by-phase completion and commencement of operation of pipelines
Pipelines
West-East Pipeline II
Qinshen Pipeline
Designed capacity (mil m³/yr)
30,000
Operation schedule
In operation since 2011
In operation since 2011
8,000
More LNG receiving terminals will be put into operation in the coming years
ENN 新奥
Location
Capacity
(mil tons/yr)
Operation schedule
Gas source
Operator
Jiangsu, Rudong
3.5
In operation since 2011
Qatar
PetroChina
Liaoning, Dalian
3
In operation since 2011
Australia
PetroChina
Zhejiang, Ningbo
3
To be put into operation in 2012
Qatar
CNOOC
Shandong, Qingdao
3
To be put into operation in 2013
Papua New Guinea
Hebei, Caofeidian
Guangdong, Zhuhai
3.5
3.5
Guangdong, Jieyang
2
To be put into operation in 2013
To be put into operation in 2013
To be put into operation in 2013
Australia, Qatar
Sinopec
PetroChina
Middle East, Australia
Middle East, Australia
CNOOC
CNOOC
More than 10 national natural gas pipeline projects including West-East Pipeline III & IV, China-
Myanmar Pipeline and Shaanxi-Beijing Pipeline III will be completed and launched one by one by
the end of 2015
Sufficient gas sources ensure piped gas projects of the Group will be able to enjoy stable supply of
piped natural gas in the long run
15View entire presentation