• B-80: Production Start-up Status Full Offshore Systems Installed and Integrated during Q4 FY22 • • SPM installation Completed & Tested MOPU • SPM to FSO connection completed and established readiness to receive Oil Top Sides Commissioning and RFSU Completed • • Process Equipment calibration, commissioning and Ready for Startup completed Statuary approvals including Consent to Operate (CTO) received • Production Startup - Technical Challenges • • • . Initiated startup of both D1 & D2 wells as per plan post project completion Pre-commissioning activities taken more time than expected Pre-commissioning completed for D2 well and gas being packed into ONGC line since 31 May 2022 D1 oil well subsea umbilical system issues are being addressed AS LINE HAZIRA H EC VADODARA D DIL LINE "NOT TO SCALE 9