Key Project Updates - Vijayanagar 5mtpa Brownfield Project • Constrution activities for all packages underway • • • Refractory erection underway for BF package One Convertor erection completed at Steel Melt Shop Equipment erection underway at Hot Strip Mill • Project to be completed by end of FY24 Coke Oven Plant • . 1.5 mtpa Coke Oven fully completed with commissioning of Battery B (0.75 mtpa) in August 2023. Battery A commissioned in FY23 Capacity enhancement of further 1.5 mtpa to support the 5 mtpa steel making expansion. Phased commissioning from Q1 FY25 JSW Steel Corporate Presentation: October 2023 JSW Steel Converter vessel erected at SMS Top Recovery Turbine erection at BF 45