Investor Presentaiton
Grid Vision 2030
Historical Iron Lady OHTL
will be modernized by
2020
around 135 M€
Huittinen - Forssa 400 kV OHTL by
2030
around 30 M€
Finland's electricity
transmission in 2030
Forest Line 400kV
Oulu - Petäjävesi
2022
around 100 M€
HVDC link
between Sweden and Finland by
2030
around 220 M€
800 MW
Production surplus
1,200 MW
Imported
FELL LINE
Third 400 kV AC interconnection
between Sweden and Finland
2025
around 200 M€
Doubling the Lake Line 400kV
Nuojua - Huutokoski by
2030
around 100 M€
Reinforcement of Helsinki
region network
2025 - 2035
around 60 M€
Extension of the Forest Line 400kV
Petäjävesi - Hikiä by
2030
around 60 M€
+800 MW
-400MW
FennoSkan 1
+800 MW
THE NEW KVARKEN
700 MW
Total of 33 investments projects to be completed in 2018
Fingrid Debt Investor Presentation
COASTA
ASTAL LINE
RIVER LINE
FOREST LINE
700 MW
1400 MW
Iron Lady II
2,300 MW
Wind power
+1,200 MW
Nuclear power
P1
+1,000 MW
+500 MW
with smart grid
solutions
700MW
Deficit in
southem Finland
FINGRIDView entire presentation