RR PROJECT TIMELINE
Advanced stage project
EXPLORATION
Between 2007 and 2011
WHY conducted
exploration including
10,000 metres drilling, 77
holes, all mineralized.
RESOURCE ESTIMATE
WHY produced NI 43-101
Technical Report initial
resource estimate of 39
Million tonnes M&I
PEA STUDY
PFS REPORTS
PFS-Stages-1 and 2
presented an optimized
proprietary HCI process with
higher product purity and
recoveries, thus substantially
improving project economics.
Final PFS report with demo
plant design and techno-
economic project study is
expected in Q3, 2022
WHY completed NI 43-
101 Technical Report PEA
Study and updated
resource estimate of 43
Million tonnes M&I.
MINING PERMIT
2019 The Company completed
Environmental Assessment and
Environmental Baseline Study and
submitted its Mine Plan Permit
Application.
Permit is expected in Q4 2022
2007
2009
2013
2019-22
目
2019/22
WHY.V | October, 2022