Investor Presentaiton
Liddell replacement is AGL's preferred option compared
with the proposal to extend the life of Liddell
Liddell replacement
Preferred option
Liddell Power Station closed in 2022 and repurposed with series of
investments in new, low emissions generation and upgrades to
existing generation
Staged approach to bring new investment online ahead of Liddell
retirement
Each phase will track timing, deliverables and completion dates of each
new investment
Newcastle gas peaker
250MW or other NSW sites
Liddell extension
agl
Work undertaken at Liddell Power Station to enable AGL to operate
the station beyond 2022
-
Extending Liddell's life by five years to deliver 1000MW of peak capacity
at reduced availability
Analysis has been done to examine the costs and other risks associated
with extending Liddell
1600MW
NSW gas peaker
500MW
Demand response
up to 150MW
Liddell battery
Renewables
B
Bayswater upgrade
DOO 250MW
NSW pumped hydro
100MW
Feasibility
Liddell synchronous condenser
Inertia and reactive power
Total capital investment: -$1,360m (-$490m in stage 1 projects)
Levelised cost of energy: $83/MWh
Asset life: 15 to 30 years
Investor Day | 13 December 2017
اليم
Total capital investment: -$920m
Levelised cost of energy: $106/MWh
Asset life: five years
9View entire presentation