Investor Presentaiton
Automation, procurement and scale are key to bringing Global
Operations to the next level
1. Automation to mitigate growth in blue-collar FTE
# of FTE release through automation,
original plan
9%
Salary¹ (Direct labour)
~600
-500
-200
>1,000
19/20 20/21 21/22 22/23
Due to longer component lead
times, the timeline of the
programme is extended into
Q1 2023/24
2. Continuously work with procurement costs and supply risk mitigation
•
Run sourcing tenders
•
Expand supplier base
55%
•
Reduce risk of supply disruptions
•
• Increase competitive pressure
In 2022/23 we expect double-digit
raw materials price increase
•
Implement new materials
Materials (RM & SFG)
100
DKK -450m
CAPEX investment over
four years (19/20 - 22/23)
DKK
0%
Like-for-like
material costs
time
Costs levels to remain at 19/20 levels
3. Efficiency and scale on global functions
100%
Keeping FTEs stable, while
increasing production output
Production costs¹
1) FY 2021/22 Cost of goods sold, DKK 7,050m
39
0%
湔
Global functions
• ☐
Volume output