Update on Vogtle Units 3 & 4
• 3 to 6 months added to expected in-service dates for each unit
-
Unit 3: Q4 2022 thru Q1 2023
.
—
- Unit 4: Q3 2023 thru Q4 2023
Georgia Power's share of total capital cost forecast increased $920 million
- Recorded after-tax charge of $686 million
- Includes $480 million for Georgia Power's share of cost and schedule changes
- Includes $440 million for incremental costs expected to be borne by Georgia Power under
co-owner agreement
- Co-owner interpretation of sharing and tender provisions could result in up to an
additional $460 million of incremental costs based on current project capital cost forecast
Schedule extension beyond November 2022 and 2023 requires affirmative vote from
owners to proceed with the project (co-owner agreement)
- Voting process is underway and expected to conclude March 8th
- Georgia Power has voted to proceed