Update on Vogtle Units 3 & 4 • 3 to 6 months added to expected in-service dates for each unit - Unit 3: Q4 2022 thru Q1 2023 . — - Unit 4: Q3 2023 thru Q4 2023 Georgia Power's share of total capital cost forecast increased $920 million - Recorded after-tax charge of $686 million - Includes $480 million for Georgia Power's share of cost and schedule changes - Includes $440 million for incremental costs expected to be borne by Georgia Power under co-owner agreement - Co-owner interpretation of sharing and tender provisions could result in up to an additional $460 million of incremental costs based on current project capital cost forecast Schedule extension beyond November 2022 and 2023 requires affirmative vote from owners to proceed with the project (co-owner agreement) - Voting process is underway and expected to conclude March 8th - Georgia Power has voted to proceed 9