Investor Presentaiton
Ashita Power 2
Project Details: Leo (phase#2) 17.0 MW
Yamaga C Project
Project Leo Details
Business Type
:
Solar power plant
31
SERMSANG
POWER CORPORATION
Project Owner
Investment Type
Investment Percentage
: Ashita Power 2 (GK Company)
: Through SEG, as TK Investor, under GK-TK Investment Structure
:
100.0%
: 1,413 1,460 KWh/sq.m./annum
Solar Irradiation*
Location
:
Shizuoka, Japan
Installed/PPA MW
:
22/17.0 MW (Phase#2)
Solar Cell Technology
:
Land Details
:
Polycrystalline Silicon
Approximately: 750 rais (surface right)
Yamaga C Project
Project Status
:
Under Development
Target Financial close
:
End of Sep-2022
Target SCOD date
:
Q4-2024
Power Purchaser
: Tokyo Electric Power Co., Inc
Purchase Price
:
Purchase Term
:
Under Fit Scheme of JPY 36/KWh
17 years
Tax Incentive
GK-TK Structure
•
TK distribution of GK Company to TK investor can be used as tax
deductible expense at GK Company level
*Source: (i) New Energy and Industrial Technology Development Organization
(ii) Power Plant Analysis Report, Mitsui Chemicals Inc.View entire presentation