Investor Presentaiton
Summary of BOT Projects
MBL
Creating Highways to Success
Project
Project
Stake
State
Client
Length
Concession Project
Period
Type
Status
COD/
Expected
CoD
Seoni-Balaghat-Rajegaon
100%
MP
State
Project
114.0
15 yrs
Toll
Operational
February
2008
Waraseoni-Lalbarra Road
100%
MP
State
Project
18.3
15 yrs
Toll +
Annuity
Operational
August
2015
Bikaner-Suratgarh
99.89%
Rajasthan
State
Project
172.4
16 yrs
Toll
Under
Construction
March 2017
Gagalheri-Saharanpur-
Yamunanagar
100%
UP/Haryana
Border
NHAI
51.5
17 yrs
HAM
Under
Implementation
Agreement
signed on
27.05.2016
Chutmalpur-Ganeshpur &
Roorkee- Chutmalpur-
Gagalheri
100%
Uttarakhand &
Uttar Pradesh
NHAI
53.3
17 yrs
HAM
Under
Implementation
Agreement
signed on
27.05.2016
Tarsod to Fagne
51%
Maharashtra
NHAI
87.3
15 yrs
HAM
Under
Implementation
15View entire presentation