Investor Presentaiton slide image

Investor Presentaiton

EPC Wastewater Treatment Facility - Mumbai Sewage Disposal Project SCOPE Design, Build, Operation and Maintenance of 418 MLD Dharavi Wastewater Treatment Facility including 209 MLD Tertiary treatment facility under Mumbai Sewage Disposal Project, Stage II (Priority Works) WELSPUN ENTERPRISES LIMITED Project details 60 Months for Design Build, Contract period 15 years of operation and maintenance Welspun Enterprises share in JV 80% Jhu Airport) Sea Princess Khar West Pali Airport Mumbai Airport Santacruz Colibar Vakola Bandra East Bandra Bandra Wes Dharavi Maunga Mahim Bay Probria DJM Sion Anik Naga Kowada Kafem Exp Wadala Status LOA received on May 27, 2022 Project Commencement date - July 4, 2022 Total consideration of ~46,360 Mn (inclusive of GST) Preparatory technical studies and basic engineering in progress 30
View entire presentation