TBS Overview
PT Minahasa Cahaya Lestari Sulut-3 Project
CFSPP Sulut-3 (2X50 MW)
North Minahasa,
North Sulawesi Province,
Indonesia
•
Project Overview
Partnership composition: PT TBS Energi Utama Tbk (90%),
Sinohydro Corporation Limited (10%)
PPA signed on 7th April 2017, and effective on 10th January 2018
"
Contract Period: 25 years
☐
Project Cost: US$ 209 million
EPC Contractor: Sinohydro Corporation Limited
Progress Updates (as of 31 December 2020)
Status
Land acquisition completed
Detailed engineering design completed
Subject
Remarks
Land Acquisition
Completed
Engineering
Completed
Procurement
Completed
Construction
In-Progress
•
Finished civil works (structure) for coal handling system
•
All shipments procurements completed
•
Finished turbine and generator installment
Circulating Water Pump ("CWP") works in progress
Balance of Plant facilities (Water Treatment Plant, Waste Water Treatment Plant, Coal
Handling System and etc) on progress (civil, mechanical and electrical)
www.tbsenergiutama.com
•
Continuing work on ESP #2 insulation and coal shed structureView entire presentation