Adani Group: Repeatable, robust & proven transformative model of investment
Activity
Performance
Phase
Origination
Analysis & market
intelligence
Viability analysis
Strategic value
•
Development
Site Development
•
Site acquisition
Construction
Operations
Operation
•
.
Life cycle O&M
planning
•
adani
Ports and
Logistics
Post Operations
Capital Mgmt
Redesigning the
capital structure of
the asset
Operational phase
funding consistent
with asset life
India's Largest
Commercial Port
(at Mundra)
Highest Margin
among Peers
Concessions and
regulatory agreements
Investment case
development
Longest Private HVDC
Line in Asia
(Mundra Mohindergarh)
Highest line
availability
Engineering & design
Sourcing & quality
levels
Equity & debt funding
at project
Largest Single Location
Private Thermal IPP
(at Mundra)
High declared
capacity of 89%1
Asset Management
plan
648 MW Ultra Mega
Solar Power Plant
(at Kamuthi, Tamil Nadu)
Constructed and
Commissioned
nine months
in
In FY20 issued seven
international bonds across the
yield curve totalling-USD4Bn
All listed entities maintain
liquidity cover of 1.2x-2x
as a matter of policy.
1. FY20 data for commercial availability declared under long term power purchase agreements;
14%
33%
47%
31%
55%
20%
March 2016
March 2020
PSU - Pvt. Banks
• Bonds