Next Steps Support from Parliament by August 12th is a condition for Sithe / Blackstone participation - The Project is a major undertaking for Guyana and it will require widespread support to be successful Without such support at the next sitting of Parliament, Sithe cannot continue to fund development expenses Complete Environmental and Technical Due Diligence - In progress Lender (IDB and CDB) Approvals IDB scheduled to present project for board approval on October 30, 2013 Missing this board date would prevent the achievement of financial close within the EPC price validity period IDB will not approve the Project without the relevant Parliamentary approvals GOG to Complete Access Road by Year End GoG awards contracts for Sections 2B and the Kuribrong River Bridge by August 12, 2013 FINANCIAL CLOSE AND START OF CONSTRUCTION TARGETED FOR 4TH QUARTER 2013 19 SITHE GLOBAL