Next Steps
Support from Parliament by August 12th is a condition for Sithe / Blackstone
participation
-
The Project is a major undertaking for Guyana and it will require widespread support to be
successful
Without such support at the next sitting of Parliament, Sithe cannot continue to fund
development expenses
Complete Environmental and Technical Due Diligence
-
In progress
Lender (IDB and CDB) Approvals
IDB scheduled to present project for board approval on October 30, 2013
Missing this board date would prevent the achievement of financial close within the EPC price
validity period
IDB will not approve the Project without the relevant Parliamentary approvals
GOG to Complete Access Road by Year End
GoG awards contracts for Sections 2B and the Kuribrong River Bridge by August 12, 2013
FINANCIAL CLOSE AND START OF CONSTRUCTION
TARGETED FOR 4TH QUARTER 2013
19