Investor Presentaiton
Infrastructure & Market Development
■ Market development by construction
☐
of distribution backbone
Delivering gas to RD by developing
pipeline or modifying system in station
■ Customer attachment to build acccess
until last mile
Customer Attachment RD III
Additional Volume: 1.3 MMscfd
Operation: 2018
Market Development in Dumai
16"& 24"
119 km
Potential of 95 MMscfd
Plan of Operation : 2019
Market Development in Purwakarta
8-16" 15 km
Potential of 5.38 MMscfd
Plan of operation : 2019
Tarakan
Market Development in Gresik, Lamongan and
Tuban
Phase 1: 24"-11.5 km
Potential of 21 MMscfd
Operation: 2018
Customer Attachment RD II
Additional Volume: 2 MMscfd
Operation: 2018
Customer Attachment RD I
Additional Volume: 6 MMscfd;
Operation: 2018
Development of Gas Infrastructure in West Java
6-12": 39 km;
Reserved capacity of 14.30 MMscfd
Sorong
pgn