Project Development Indicative Timeline The Company's indicative timeline targets: ■ Q1 2022 Final Investment Decision. ■ Q2 2022 Commencement of Construction. Q3 2023 Commencement of Production. Marketing and Offtake PSG Optimisation Tests Product Qualification PSG Engineering Final Regulatory Approvals Early Works and Long Lead Procurement Project Financing and Due Diligence Final Investment Decision Detailed Design and Procurement Construction Commissioning Production Start Renascor Resources Ltd | ASX: RNU Q1'21 Q2'21 Q3'21 Q4'21 Q1'22 Q2'22 Q3'22 Q4'22 Q1'23 Q2'23 Q3'23 renascor.com.au 21