ADB-PLN Electrical Grid Strengthening Program
|West Kalimantan Power Grid Strengthening
Project Cost: $130m
Financing
$99 million ADB (including 49.5 million co-financing from AFD);
$2.0 million TA (grant from CEFPF)
Approval: 27 Aug 2013
.
.
SCOPE
230 MW 83 km cross border transmission
interconnection
P1: 275 kV transmission line(TL) from Bengkayang
to Jagoibabang
.
150 kV TL from Bengkayang to Tayan
• 150 kV TL from Tayan to Sekadau ( using loan saving)
• Associated substations (SS)
PLN energy purchase: 50 MW base load take or pay + 180 MW 6
hours take and pay = total 650GWh/yr
PLN purchase price: 60% cost savings/KWh
PLN savings: estimated $100m/yr
Performance guarantee: to help fast track project
$35m with $25k/day delay cost
interconnection agreement signed on 30 June 2013
Jagoibabang
275/150 kV Bengkayang SS
WEST KALIMANTAN, INDONESIA
Date 23rd Feb 2021
20 kV Ngabang SS
150/20 kV Sanggau S$
Legend
150/20 kV Sekadau SS
150/20 kV Tayan SS
International Borders
:275 kV Transmission line
: 150 kV Transmission line
275 kV Substation
150 kV Substation