Project Development
The Plant
2x110MW Banjarsari Power
Plant
Bukit Asam
Power Generation Projects
Status
•
PTBA (59.75%), PJB (29.15%), NII (11.10)
Investment of USD320 Mn
Coal Consumption: 1.4 M tpa
Estimated Commercial Date: 4Q14
2x620MW Banko Tengah
Plant
800-1200MW Peranap Power
Plant
3x10MW Power Plant for
internal use
2x8MW Power Plant for
internal use
•
•
PTBA (45%), China Huadian Hong Kong Company Ltd (55%)
Investment of USD1.6 Bn
Coal Consumption: 5.4 M tpa
PPA signed in September 2012
Currently in the process of Financial Closure
Estimated Commercial Date: 2018
PTBA (Majority in Mining), PLN (Majority in Power Plant), TNB (Majority in
Transmission)
• Investment of USD1.8 Bn
• Coal Consumption: up to 8.4 M tpa
Currently in the process of preparation for the FS of power plant & transmission
Estimated Commercial Date: 2018
• Located at Tanjung Enim Mine
• Investment of USD42 Mn
•
Coal consumption: 0.15 Mtpa
In operation since October 2012
Located at Tarahan Port
• Investment of USD29.12 Mn
Coal consumption: 0.10 Mtpa
In operation since December 2013