SEMPRA 5-Year Capital Plan
Sempra Infrastructure Growth Pipeline
LNG + NET-ZERO SOLUTIONS²
ECA LNG Phase 13
(~3 Mtpa)
Port Arthur LNG Phase 13
(~13 Mtpa)
Cameron LNG Phase 2
Train 1-3 Debottlenecking
Commentary
.
COD expected summer 2025
•
Targeted Train 1 COD 2027, Train 2 COD 2028
.
Targeting online in stages prior to Cameron LNG Train 4
1
Status
Construction
Construction
Development
(~1 Mtpa)
Train 4
•
Progressing with Cameron LNG Members + FEED contractors
(-6 Mtpa)
•
SI plans to sell its offtake back-to-back under long-term contracts
Development
•
HOAS: PKN ORLEN
Port Arthur LNG Phase 2
.
HOAS: INEOS
Development
(~6-13 Mtpa)
Vista Pacifico LNG
•
MOUS: Total + CFE
Development
(~2 Mtpa)
ECA LNG Phase 2
.
HOA: ConocoPhillips | MOUS: Total + Mitsui
Development
(-12 Mtpa)
Hackberry CS
ENERGY NETWORKS
Topolobampo Terminal³
GRO Expansion³
Port Arthur Pipeline
CIP Expansion
•
Participation agreement: Total, Mitsui + Mitsubishi
Development
Commentary
Status
•
•
.
COD targeted Q4-2023
COD targeted 1H-2024
Construction completed, pending regulatory requirements
Expanding gas pipeline delivery to ECA LNG Phase 1+ Baja
2.0 Bcf/d Louisiana connector
Commissioning
Construction
Development
.
Delivering gas to Cameron LNG Phase 2
Development
Pitic Pipeline
CLEAN POWER²
Cimarrón
Developing gas infrastructure between Sonora + Baja
Commentary
Executed 20-year PPA with Silicon Valley Power | 300 MW
The ability to complete major construction and development projects is subject to a number of risks and uncertainties.
Projected nameplate capacity represents 100% of the project, not Sempra's ownership share. Capacities are illustrative and approximate.
As these projects have reached FID, they are reflected in financial plan.
1234
1.
2.
3.
4.
The current arrangements do not commit any party to enter into definitive contracts, which are subject to negotiation.
Development
Status
Development
SEMPRA | 19View entire presentation