CapitaGreen: construction on track to be
completed by end 2014
Level 40
•
Current development activities include:
Completed structural work on 40th floor (top floor)
Ongoing installation of wind scoop
• Commencement of Sky Forest works
·
Ongoing interior works up to 26th storey
• External Façade glazing installation up to 34th storey
CCT's 40% interest
CCT's 40%
interest in MSO
Trust
Progress
payment as
at Jun 2014
Balance by
progress
payment
■(2)
(1)
MSO Trust's debt
S$356.0m
(S$290.0m)
S$66.0m
Equity inclusive of
shareholder's loan
S$204.0m
(S$130.4m)
S$ 73.6m
South-West view of CapitaGreen
Notes:
(1) MSO Trust has secured committed bank loan facilities of up to S$890m (100% interest)
(2) Ongoing capital requirement by progress payment until 2015
Total
S$560.0m
(S$420.4m)
S$139.6m