31 CapitaGreen: construction on track to be completed by end 2014 Level 40 • Current development activities include: Completed structural work on 40th floor (top floor) Ongoing installation of wind scoop • Commencement of Sky Forest works · Ongoing interior works up to 26th storey • External Façade glazing installation up to 34th storey CCT's 40% interest CCT's 40% interest in MSO Trust Progress payment as at Jun 2014 Balance by progress payment ■(2) (1) MSO Trust's debt S$356.0m (S$290.0m) S$66.0m Equity inclusive of shareholder's loan S$204.0m (S$130.4m) S$ 73.6m South-West view of CapitaGreen Notes: (1) MSO Trust has secured committed bank loan facilities of up to S$890m (100% interest) (2) Ongoing capital requirement by progress payment until 2015 Total S$560.0m (S$420.4m) S$139.6m Capita Commercial CapitaCommercial Trust Presentation August 2014 Trust