Northland Power Capitalized Growth & Strategic Overview
Baltic Power
Established position in Eastern Europe through Baltic Power offshore wind project
Up to 1.2 GW
Poland is an attractive new country within the EU, with growth potential in
onshore and offshore
Granted a 25-year fixed price Contract for Differences ("CfD")
Partnership provides local presence and scale resulting in enhanced returns
due to synergies in development, construction and operation
Progress the project to financial close by completing design, certification,
consents, procurement strategy, optimisation and financing plan
2021
Acquired
interest/ Secured
CfD
2022
Timeline For Baltic Power Development
2023
Project design
Achieve Financial
and optimization
Close
2024
2026
Baltic Power
Expect to start
Construction
Expected
Commercial
Poland
0
NORTHLAND
POWER
Operations