Northland Power Capitalized Growth & Strategic Overview slide image

Northland Power Capitalized Growth & Strategic Overview

Baltic Power Established position in Eastern Europe through Baltic Power offshore wind project Up to 1.2 GW Poland is an attractive new country within the EU, with growth potential in onshore and offshore Granted a 25-year fixed price Contract for Differences ("CfD") Partnership provides local presence and scale resulting in enhanced returns due to synergies in development, construction and operation Progress the project to financial close by completing design, certification, consents, procurement strategy, optimisation and financing plan 2021 Acquired interest/ Secured CfD 2022 Timeline For Baltic Power Development 2023 Project design Achieve Financial and optimization Close 2024 2026 Baltic Power Expect to start Construction Expected Commercial Poland 0 NORTHLAND POWER Operations Northland Power | 15