Capricorn Copper Restart Status
ESS Remediation
•
■
•
ESS sublevel cave mining resumption is Phase 2 of Capricorn Copper Recovery Plan
Critical path is dewatering timeframe with ground support renewal being conducted in parallel with
dewatering progress
Underground dewatering and ground support rehabilitation commenced
Conservative stoping restart schedule to manage for potential risk of flow of fine, wet ore from draw
points
Other possible historical analogous flooded mines are Big Bell and Mt Lyell. 29M in dialogue with prior
operators to gain additional knowledge
Future Resilience
•
•
Conversion to 100% recycled water use for operations positions the site with a negative water balance
Reinstatement and improvement of clean water diversion
Replacement warehouse, workshops and water treatment plant to be re-established at higher locations
All weather roads constructed to critical wet-season water management infrastructure
ESS Ground Support Rehabilitation