Li-Cycle Results Presentation Deck
European Hub: Li-Cycle Proprietary Process and Operational Know-
How Accelerates Production of Lithium Carbonate(1)
Expedited Flowsheet
Black Mass
Leaching
MHP(2)
(Co-Ni-Mn)
Precipitation
Lithium
Carbonate
Precipitation
Portovesme Hub Key
Milestones Timeline
Brownfield Site: Portovesme, Italy
> Processing Capacity: Up to 70,000 tonnes
black mass per year
> End-Products (in tonnes per year):
●
●
●
Portovesme Hub Project Highlights
Lithium Carbonate: -15,000 tonnes (3)/yr
Nickel contained: ~18,000 tonnes/yr
Cobalt contained: ~2,250 tonnes/yr
Mid-2023 - Mid-2024
Definitive Feasibility Study
Brownfield: Lowering capital intensity by repurposing
existing metallurgical site infrastructure and
equipment with access to operating workforce
Technology: Fast tracking Li-Cycle's state-of-the-art
hydrometallurgical technology to Europe
Feedstock: Supplied from both Li-Cycle's growing
European Spoke network and Glencore's commercial
network
Funding: Contemplates competitive long-term
financing from Glencore to fund Li-Cycle's full share of
the capital investment
Late 2024 - Late 2026
50-70kt Construction
Late 2026 - Early 2027
Commence Commissioning
Li-Cycle
(1) Portovesme Hub to commence construction upon completing DFS and subject to Final Investment Decision; (2) MHP refers to mixed hydroxide product; (3) Projected to produce approximately 15,000 to 16,500 tonnes of lithium
carbonate
11View entire presentation