Project Execution Construction schedule - Origin 2 2021 Project Development Site Screening Site Selection Site Evaluation Owner's Engineer Selected FEL1 Engineering Partner Selected Contractor Selection 2022 2023 Construction Contract Executed Front End Design (Assess, Select, Define) February 2022 • • • 2024 2025 Recent accomplishments/status - - Selected site in Geismar, Louisiana, subject to finalization of economic incentives DONE Selected Hunt, Guillot & Associates as owner's engineer DONE Objectives by end of Q1 2022 Announcement of selected site DONE Objectives by end of Q3 2022 - - - General equipment arrangements and flow diagrams Equipment selection and sizing; value engineering Objectives by end of Q4 2022 Final equipment, instrument, electrical specification and lists FEED Package Complete Detailed Engineering Construction Mechanically Complete Construction & Fabrication Start Commissioning & Start-Up Start-Up ORIGIN 17