ADB-PLN Electrical Grid Strengthening Program slide image

ADB-PLN Electrical Grid Strengthening Program

Transmission Investment Challenges. Date 23rd Feb 2021 Changing context Energy policy, medium and long-term planning of PLN, demand projection. " " Land acquisition securing land and forestry permits, and rights of way from the government. Planning If planning is not done well, public or private projects can lock in long-term financial obligations for under-used assets 180 Local content requirement increasing project cost, not in accordance with the lender's procurement policy. Safeguards In particular environment, indigenous communities, and other compliance issues. Capacity building and information management organizational changes, staff turn over, project supervision. ADB 8
View entire presentation