NHPC Capacity Addition and Financial Overview
NHPC -Subsidiary Company's Project Under Clearance
S.No
Projects
Installed
Capacity (MW) Energy (MUs)
Design
Cost (In Cr.) &
PL
1
Kirthai-II
930
3330
(6x140 + 2x35 +
6384
(Feb'20)
2x10)
UT of J&K
33
एनएचपीसी
NHPC
Status
•MOU has been signed between NHPC Ltd. and JKSPDCL
on 03.01.2021.
•The project shall be executed by M/s CVPPPL on the same
terms and conditions of that of Pakaldul, Kiru & Kwar H E
Projects.
•The Appraisal has been transferred in the name of CVPPPL
by CEA on 29.12.2021.
•
•Defence Clearance was accorded by MoD on 24.03.2022.
• Extension of validity of appraisal up to 13.06.2024 was
accorded by CEA on 29.08.2022. Balance investigation
works are in progress in compliance to DPR concurrence.
EAC had recommended for grant of Environment
clearance (EC) to the project on 15.04.2021. MOEF vide
letter dated 24.5.2021 has intimated JKSPDC that EC shall
be accorded after Stage-I Forest Clearance is granted.
•Application for FC on Parivesh Portal of MOEF&CC
submitted successfully on dated 19.10.2022View entire presentation