Modernising Agreements and Transition to Renewables
Raising our system capacity
Max month*
Mt
Prior best performance
Max quarter*
Mt
Estimated
Capacity
Max annual
Mt
Mid term*
Mt
**
Mine
370
349
338
345-360
Rail
362
351
338
350-360
Ports
393
357
338
360+
System
*Annualised rates |
362
351
338
Mid-term defined as upon completion of the next tranche of new and replacement mines
Rio Tinto
©2021, Rio Tinto, All Rights Reserved
345-360
System capacity will be delivered by:
- Rio Tinto Safe Production System driving
-
improved productivity
Improved interface efficiencies across mine,
plant, rail and ports
Modest capital investment, including two
additional rail consists
Requires commissioning of replacement mines,
including Western Range, Bedded Hill Top and
Hope Downs 2 and Brockman Syncline 1 to reach
and sustain capacity