Nova Mine Design & Schedule Nova igo Grade control 100% complete by end CY17 Capital development substantially complete by end FY18 C5 Bollinger DEVELOPMENT Pre 30 Jun Post 30 Jun 2017 2017 STOPING Completed 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 15