The Africa Challenge – Khemisset Potash Project

ENVIRONMENTAL APPROVAL Environmental approval for the project remains outstanding, however progress has been made on a number of fronts: ESIA first submitted 30 November 2020 Mining Permit awarded 26 January 2021 ESIA third draft submitted (including revised water sourcing proposal using waste water from local treatment facility) 26 July 2022 Technical submissions made to environmental and water agencies for review. December 2022 Public consultation completed on 24 January 2021 following consultation with local communes ESIA second draft submitted (addressing issues raised after initial draft) 12 August 2021 Met with technical authorities on 28 October 2022 who confirmed only minor finalisations required to complete the submission. 13