The Africa Challenge – Khemisset Potash Project
ENVIRONMENTAL APPROVAL
Environmental approval for the project remains outstanding, however progress has been made on a number of fronts:
ESIA first submitted
30 November 2020
Mining Permit awarded
26 January 2021
ESIA third draft
submitted (including
revised water sourcing
proposal using waste
water from local
treatment facility)
26 July 2022
Technical
submissions
made to
environmental
and water
agencies for
review.
December
2022
Public consultation
completed on 24
January 2021
following consultation
with local communes
ESIA second draft
submitted (addressing
issues raised after
initial draft)
12 August 2021
Met with technical
authorities on 28 October
2022 who confirmed only
minor finalisations
required to complete the
submission.
13View entire presentation