Investor Presentaiton
2016 Integrated Resource Plan
A flexible, balanced plan that reflects our commitment to a low-carbon future and
pursuant to the Oregon Clean Electricity Plan
Renewable procurement
• Procurement of renewables (100 MWa) to meet Oregon Clean Electricity Plan
.
.
Potential benchmark resource identified
Timeline:
•
December 2017: IRP acknowledged
May 2018: Final RFP issued
June 2018: RFP proposals received
End of 2018: Completion of RFP process, issue Notice To Proceed
Capacity need
Executed contracts for 300 MWs through bilateral procurement processes:
• 200 MW of annual-capacity with five-year terms beginning 2021
• 100 MW of seasonal peak capacity during summer and winter periods with a
five-year term beginning 2019
Portland General Electric
20
20View entire presentation