The Plant
2x110MW Banjarsari Power
Plant
2x620MW Banko Tengah
Power Plant
800-1200MW Peranap Power
Plant
Bukit Asam
Power Plants
Status
•
•
•
•
•
•
•
•
•
•
PTBA (59.75%), PJB (29.15%), NII (11.10%)
Investment of USD350 Mn
Coal Consumption: 1.4 M tpa
In operation since June 2015
PTBA (45%), China Huadian Hong Kong Company Ltd (55%)
Investment of USD1.6 Bn
Coal Consumption: 5.4 M tpa
Facility Loan Agreement of US$1.2 Bn has been signed with Cexim in March 2015
Financial Closing will be finalised in 2H15
Groundbreaking will start at the beginning of 2016
Commercial Operating Date will be in 2019
PTBA (Majority in Mining), PLN (Majority in Power Plant), TNB (Majority in
Transmission)
Investment of USD2.4 Bn
Coal Consumption: up to 8.4 M tpa
Currently in the process of preparation for the FS of power plant & transmission
• Commercial Operating Date: 2020
3x10MW Power Plant for
internal use
.
Located at Tanjung Enim Mine
•
Investment of USD37 Mn
• Coal consumption: 0.15 Mtpa
•
In operation since October 2012
2x8MW Power Plant for
internal use
•
Located at Tarahan Port
•
•
Investment of USD21 Mn
Coal consumption: 0.10 Mtpa
In operation since December 2013