Investor Presentaiton
Vogtle 3 & 4 - Cost Update
(Georgia Power's share)
Total capital cost forecast increased by $920 million to address
updated projected in-service dates, construction productivity,
increased support resources, and replenishment of contingency
Estimated Cost of Project ($M)
Base project capital cost forecast through Q1 2023/Q4 20231,2
$10,251
Construction contingency estimate
150
Total project capital cost forecast 1,2
$10,401
Net Investment as of December 31, 20212
(8,442)
Remaining estimate to complete
$1,959
Includes approximately $590 million of costs that are not shared with other Vogtle Owners and approximately $440 million of incremental cost under relevant cost-sharing and tender provisions. Excludes financing costs expected to be capitalized through AFUDC of
approximately $375 million, of which $195 million has been accrued through December 31, 2021.
1)
2)
Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.