Investor Presentaiton
NEA
Nuclear Energy Agency
Summary
OECD
• The ABWR is the evolutionary design of the conventional BWR and
.
.
the first design, among Generation III LWR designs, with
construction and operating experiences.
The first ABWR, Kashiwazaki-Kariwa 6, was constructed on a 37
months schedule from the first reactor building structure concrete
pour to fuel load. The advanced management and construction
technologies have been developed and demonstrated through
continuous experiences of ABWR construction in Japan.
• The Shimane-3 was constructed for "On-budget and On-schedule"
with application of more advanced design and construction
methodology, just before the Fukushima accident. It was 94%
complete and construction was suspended in March 2011.
OECD NEA Workshop on Project and Logistics Management, Paris, 11th March 2014 17View entire presentation