NHPC Financial Highlights & Renewable Energy Projects
NHPC - Major Highlights during the period
एनएचपीसी
NHPC
18
Hon'ble Prime Minister of India laid the foundation Stone of the Kwar Hydroelectric Project (540 MW) on 24.04.2022
and Cabinet Committee on Economic Affairs (CCEA) chaired by Hon'ble Prime Minister of India accorded
investment approval to the project at an amount of Rs. 4526.12 crore.
NHPC as an intermediary procurer awarded 2000 MW ISTS connected solar PV Power Project to 5 nos. of developers
with a trading margin of 7 paise/unit. Out of 2000 MW, 320 MW was awarded to M/s Avaada Energy Pvt. Ltd. at
Bikaner, Rajasthan which has been fully commissioned on 10.12.2022.
Power Purchase Agreement (PPA) has been signed between Bundelkhand Saur Urja Limited (BSUL) and Uttar
Pradesh Power Corporation Limited (UPPCL) for Kalpi Solar Power Project on 28.04.2022 at a fixed tariff of Rs.
2.68/unit. Further, the project has been synchronized with the Grid and commissioned partially on 09.07.2022.
Bulk Power Supply Agreement (BPSA) has been signed between Lanco Teesta Hydro Power Limited (LTHPL) and
Chhattisgarh State Power Distribution Company Limited (CSPDCL) at Raipur on 21.07.2022 for power generated from
500 MW Teesta-VI H.E. Project for a period of 40 years from COD.
NHPC has inked an MOU with the Investment Board of Nepal at Kathmandu, Nepal on 18.08.2022 for development
of 750 MW West Seti and 450 MW SR-6 hydroelectric projects. NHPC also signed MOU with PTC India Limited for
Power Sales Arrangement of these projects on 30.08.2022.
NHPC Renewable Energy Limited (a wholly owned subsidiary of NHPC Limited) has signed MOU with Govt. of
Rajasthan on 24.08.2022 at New Delhi for "Development of 10,000 MW Ultra Mega Renewable Energy Power Park" in
the State of Rajasthan.View entire presentation