NHPC Capacity Addition and Financial Overview
NHPC Standalone Projects Under Clearance
Installed Design
S.No.
Projects
Capacity Energy
Cost
(In Crore)
3
Sawalkot
(6x225+1x56)
UT of J&K
(MW)
1856
(MUs)
7995
& PL
22704.80
(Completion)
4
Uri-I Stage-II
(2x120)
240
932.6
UT of J&K
2526.79
(Completion)
Total
3116
12393.6
35594.59
एनएचपीसी
NHPC
•
•
•
.
•
•
.
•
•
•
•
•
Status
MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021.
The project shall be executed by NHPC on BOOT basis for the period of 40 years.
Agreement for handing over / taking over signed between NHPC and JKSPDC
on 11.12.2021 & NHPC has taken over the Project.
The Ministry of Power has accorded approval on 12.07.2022 for incurring
expenditure on pre investment activities for an amount of 973 crore at
Nov.2021 Price Level.
Process for obtaining forest clearance has been initiated.
CEA vide letter dated 27.12.2022 vetted the cost estimates at completion level
for an amount of 22704.80 crore including ₹4593.41 crore for IDC and ₹1124.20
crore for enabling infrastructure.
Gram Sabha meetings have been conducted for all 30 villages for FRA
compliance. All Gram sabha resolutions have been submitted by Gram
Panchayats (GPs) to the respective DCs. NOCs under FRA for GPs in Udhampur,
Reasi and Ramban Districts were issued by respective DCs on 28.11.2022,
05.12.2022 and 24.02.2023 respectively under FRA, 2006.
Identification and verification of CA area of Ramban and Udhampur Districts are
under process.
MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021.
The project shall be executed by NHPC on BOOT basis for the period of 40 years.
MOEF&CC vide letter dated 10.06.2021 has conveyed the approval to the TOR.
EIA/ EMP studies is in progress.
Process for obtaining forest clearance is in progress.
DPR concurred by CEA on 07.03.2023 amounting to ₹2526.79 crore at
completion level including 249.45 crores for IDC and 26.20 crores for enabling
infrastructure.View entire presentation