Currency and Interest Rate Outlook
K
KASIKORNTHAI
EEC Progress
ธนาคารกสิกรไทย
开泰银行 KASIKORNBANK
Expected
Projects
Amount
Owner
Contract
Signed
Beginning
Name of the selected JV
Construction
project
completion
High-Speed Rail Linking 3 Airports
Bt224.5bn
State Railway of
Thailand
Oct 2019
Charoen Pokphand Group (CP) led
Consortium
(CP, Italian Thai, CH. Karnchang, China
Railway Construction Corp)
4Q21
2025
U-Tapao Airport and Aviation City
Bt290bn
Royal Thai Navy Jun 2020.
Bangkok Airways led Consortium
(Bangkok Airways, BTS, Sino-Thai)
4Q21
2025
GPC
Bt84.4bn
Jul 2021
(Gulf Energy Development Pcl + PTT Tank
Terminal China Habour)
1Q22
(F Dock)
Laem Chabang seaport (3rd Phase)
and
Port Authority of
Thailand
for F Dock Development
and
2025
C NNC
1Q21
Bt 21.3 bn
Aug 2020
(NTL Marine + Nathalin + Zhonggang
Construction)
(Land
reclamation)
for Land reclamation project
Map Ta Phut seaport (3rd Phase)
Bt55.4bn
Industrial Estate
Authority of
Thailand
Oct 2019
PTT Tank Terminal + Gulf Energy
Development Pcl
3Q21
2026
Note As Thai Airways is restructuring and no longer as a state enterprise, Maintenance, repair and overhaul (MRO) centre has been cancelled since March 2021. Bangkok Airways is now become new potential
investor of MRO project (but the agreement has not yet finalized.)
Source: Newspaper, Eastern Economic Corridor Office of Thailand and KResearch as of April 2021