Investor Presentaiton

PLENITUDE KEY PROJECTS B STORAGE SOLAR PV ONSHORE WIND OFFSHORE WIND WORKING COUNTRY PROJECT INTEREST EQUITY INSTALLED CAPACITY (MW) YEARLY TECHNOLOGY COMPLETION PRODUCTION (GWh) Caparacena, Guillena, -- SPAIN 100% 1.020 2024-2025 2.080 Villarino, La Flota & Renopool USA Brazoria 100% 263 2022 450 USA Guajillo 100% 200 B 2024 150 SPAIN FRANCE Orense Samoussy GREECE Toumba & Mandria ITALY ITALY KAZAKHSTAN UK 100% 100 100% 90 100% 160 2025 210 2022 90 2025 250 GreenIT (PV portfolio) 51% 80 2024-2025 140 Hergo Ren. (PV portfolio) 65% 140 2024-2025 140 Shaulder 100% 50 2023 90 Dogger Bank (A, B, C) 13% 470 2023-2026 2.200 Storage: BESS production refers to annual energy dispatched. Completion represents the final construction stage excluding the grid connection, meaning that all principal components have been installed. Pre-commissioning activities fall within the construction phase. 39