Investor Presentaiton
SOUTHHARZ
POTASH
MILESTONE
H1
H2
H1
H2
CY23 CY23 CY24 CY24
H1
CY25 CY25
H2
H1
CY26
H2
CY26
H1
CY27
Clear delivery pathway
Ticking all development milestones
RECENTLY DELIVERED MILESTONES:
◉
1.
■ Küllstedt and Gräfentonna exploration licence extensions
granted by Thuringian mining authority
■ Bench scale metallurgical test work completed by K-UTEC on
core samples collected from drillholes OHM-01 and OHM-02
validated scoping study process flow design
◉
ERM Consultants appointed as both the Environmental Impact
Assessment (EIA) consultant and Spatial Planning Permitting
consultant
■ Hatch appointed to lead PFS delivery team which includes
German engineering consultants ERCOSPLAN as mining
specialists, K-UTEC as process consultants and Micon for
Resource Geology
☐
☐
Environmental baseline studies for the later EIA commenced
at three potential sites around our Ohmgebirge area
Ohmgebirge permitting process commenced with a requisite
Scoping Paper submitted to local regulatory body - full Spatial
Planning Application to be submitted by Q4 CY23
Refer to Appendix: Permitting overview
AUGUST 2023
Site selection
Pre-Feasibility
Study
Environmental
Study (EIA)
Definitive
Feasibility
Study
Project
Permitting1
Project
construction
INVESTOR PRESENTATION
15View entire presentation